When a Notice of Completion has been filed, the original contractor has how many days to record a lien?

Study for the California Landscaping Contractor (C-27) License Exam. Use flashcards and multiple choice questions with hints and explanations. Get ready for your exam!

Multiple Choice

When a Notice of Completion has been filed, the original contractor has how many days to record a lien?

Explanation:
In California, the deadline to file a mechanics lien changes when a Notice of Completion is recorded. Normally, lien rights must be exercised within 90 days after the project is completed or work ceases. But once a Notice of Completion is filed, the window narrows to 60 days. That 60-day period starts from the date the Notice of Completion is recorded, not from the original finish date. If that 60-day window is missed, the lien may be barred for that project.

In California, the deadline to file a mechanics lien changes when a Notice of Completion is recorded. Normally, lien rights must be exercised within 90 days after the project is completed or work ceases. But once a Notice of Completion is filed, the window narrows to 60 days. That 60-day period starts from the date the Notice of Completion is recorded, not from the original finish date. If that 60-day window is missed, the lien may be barred for that project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy