To be binding, change orders to a home improvement contract must contain which of the following?

Study for the California Landscaping Contractor (C-27) License Exam. Use flashcards and multiple choice questions with hints and explanations. Get ready for your exam!

Multiple Choice

To be binding, change orders to a home improvement contract must contain which of the following?

Explanation:
A change order becomes binding only when it is written and signed by both the homeowner and the contractor. This shows that both parties agree to the specific change, its cost or price impact, and any effect on the schedule, and it becomes an official part of the contract. Notarization isn’t required, and witness signatures aren’t necessary, and oral approval alone isn’t binding because there’s no reliable written record of the agreement. A proper change order typically describes exactly what is being changed, how much it costs, any time adjustments, and it includes the signatures of both parties to prove mutual consent.

A change order becomes binding only when it is written and signed by both the homeowner and the contractor. This shows that both parties agree to the specific change, its cost or price impact, and any effect on the schedule, and it becomes an official part of the contract. Notarization isn’t required, and witness signatures aren’t necessary, and oral approval alone isn’t binding because there’s no reliable written record of the agreement. A proper change order typically describes exactly what is being changed, how much it costs, any time adjustments, and it includes the signatures of both parties to prove mutual consent.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy